28th month (October 2006)
We start working on the front frame (the actual front of the motorhome).
The time consuming task this month was rolling the beams. Next month we need to make another three beams.
We start rolling |
our first front beam. |
|
|
|
And the fibreglass header |
29th month (November 2006)
By the end of this month we aim to have all the required beams for the front and hopefully welded them all together as one frame.
After having rolled all of the required beams. |
|
|
|
First the side was reconstructed |
|
|
and welded them on. |
The side (at the top) joined the front |
The 'B' pillar roof bow went on. |
The roof bows are joined |
Next month is a short month as Peter is on two weeks holiday. |
30th month (December 2006)
This month was only two weeks long (due to two weeks holiday)
During this month we continued on the front frame and moved into a new shed.
Building the frame |
and more |
complete |
Side view |
|
|
The front opening is gone. |
|
|
|
|
A glimpse of the finished product |
|
|
|
|